1st Week Report

In the first week we were all introduced to ourselves as new team members. For two days we had team building activities, what helped us during next days, as we had to choose between various topics to do one. After everyone giving theirs opinion we agreed on Metallic & Fabric Dome to be our first choice.

2nd Week Report

On Monday we were informed that our project is going to be our first choice. Knowing that, we were able to start thinking about the topic. We prepared list of questions to our supervisors, after hearing answers, we had an other meeting with our main supervisors, Abel Duarte and Fernando Ferreira, who explained us possible materials, structures of the dome etc.

3rd Week Report

In this week we started to work on our project- we divided tasks and goals among team members, we created the first draw of Gantt Chart. We also thought about use of our product-how we are going to sell it as, we decided that’s going to be a winter garden.

4th Week Report

During this week we made a logo and leaflet, we also started to work on wiki-state of the art, marketing and project management. We accomplished to do a the black box diagram and the structural drawings.

5th Week Report

In the fifth week, we did a cardboard model of our dome, we also improved our structural drafts of the dome. We started to create a material list for our dome. We continued working on wiki.

6th Week Report

We continued working on wiki, also list of materials. We started to design door and windows.

7th Week Report

We finished our wiki report and also an interim presentation.

8th Week Report

After presenting our interim report and getting feedback from supervisors and teachers, we started to improve it-some grammatical mistakes and content, everyone is working on the part they wrote before:

Introduction-Klaudia

State of the Art-Arne

Project Management- Klaudia

Marketing-Arne and Klaudia

Sustainability-Jairo and Gargely

Ethics-Bogdan

We also continued working on the design of windows and door.

9th Week Report

Student Week

10th Week Report

Meetings

1st Meeting (2016-02-25)

Agenda:

  1. Presentation
  2. Modus operandi
  3. Project proposals
  4. Electronic Logbook

Minute:

In the first meeting all of the subjects to projects were presented and briefly described by teachers. After that we were told that we had to choose three that we were most interested in and send an email with a list.

2nd Meeting (2016-03-03)

Agenda:

  1. This will be our first meeting with our supervisor(s), concerning our project's topic. With this meeting, we would like to obtain a better understanding about what is expected from us and how we should start the project.
  2. Here are some agenda points that we would like to discuss:
    • A general clarification about our project.
    • Is there already a price limit for the dome or is it a part of our research ?
    • If we build a full scale model and we have to exceed our budget in orde to build it. Is it possible to obtain extra money for the project ?
    • What about the windows: can we choose how many windows we want ? In what material should they be constructed?
    • How should the communication be with our supervisors? If we suddenly have some important questions, can we ask them immediately or should we make an appointment first ?
    • If we have some other good ideas for the dome which aren't described in the project description, can we implement them in the dome as well? Or should we really stick with the objectives that were described in the project description ?
    • What is our target ? to which people are we going to sell it to?
    • Should we make a brand for our product? (logo, name, etc)

Minute:

In the second meeting all of our questions were answered, also we were given more details about our project and possibilities of constructing the dome. We were also told to start working on our wiki.

3rd Meeting (2016-03-10)

Agenda:

  1. Continue our general research
  2. Search the standards
  3. Decisions about the materials

Questions for the meeting:

Minute:

First, we were explained that we need to precise the purpose of our dome, then all of our question could be answered. We found out that we have to make a list of all materials that we will need to design and build the dome. What is more we need to correct our Gantt Chart and work on wiki.

4th Meeting (2016-03-17)

Agenda:

  1. Continue our general research
  2. Quantity of materials and prices
  3. Structure of the nodes
  4. Marketing

Things we would like to discuss:

Minute:

5th Meeting (2016-03-30)

Agenda:

Things we would like to ask/discuss:

Minute:

6th Meeting (2016-04-06)

No agenda

7th Meeting (2016-04-14)

Agenda

Minute:

8th Meeting (2016-04-27)

Minute:

9th Meeting (2016-05-12)

No agenda

10th Meeting (2016-05-19)

Minute:

11th Meeting (2016-06-02)

Activities

Please register here all project activities

Start End Task Description Who